Garway New Community Centre Project Update

Contractural Process

A Prequalifying Questionnaire was sent to 5 Contractors in January. 4 contractors expressed an interest in tendering for the construction of the new centre. Design drawings and other tender documents were sent to those contractors in February with a required return date of 12th March for their tenders.

The tenders will be reviewed by the Project Design Team (Architects, Engineers, Quantity Surveyor and Garway Village Hall Trustee representative) on the 17th March with the intention of choosing the preferred contractor. Information on the tendering process and details of the preferred contractor will be discussed with the Big Lottery and following their approval the chosen contractor will be appointed and the final design details and a fixed price contract will be developed for the project. The scheduled start date for construction is early May.